CASE STUDY / 2024

Pressure Vessel Package — Pre-shipment QA

REGION
Northern Mexico (fabrication) for Gulf Coast (delivery)
YEAR
2024
SCOPE
Source inspection · Expediting · Capability evaluation

SCHEMATIC

What PSG covered

PROJECT SCOPE / SECTION VIEW
SOURCE INSPEEXPEDITINGCAPABILITY EPSG-COVERED STAGES

THE BRIEF

What the client needed

A US owner had qualified a Northern Mexico fabricator for a five-vessel package destined for a Gulf Coast refinery turnaround. With limited operator bandwidth and a tight turnaround window, the owner contracted PSG to embed a vendor inspector at the fabricator for the duration of the build and to run an end-of-build capability evaluation.

PSG'S APPROACH

What we did, in order

  1. 01

    Full-time vendor inspector embedded at the fabricator for 14 weeks, with daily reports in English and Spanish.

  2. 02

    Material certification verification on plate, flange, and weld consumable receipts.

  3. 03

    Witnessing of welder qualification tests, pressure tests, and dimensional acceptance.

  4. 04

    End-of-build capability evaluation written against ASME Section VIII Div 1 and the owner-specific MSE.

OUTCOMES

What the engagement delivered

  • 5
    VESSELS DELIVERED DEFECT-FREE TO SITE
  • 0
    FIELD WELD REPAIRS REQUIRED
  • 2 weeks
    AHEAD OF TURNAROUND CRITICAL PATH

RELATED

Pillars and industries that touch this work

VERIFIED BY

Manisha Sharma, Project Lead · API Authorized Inspector