CASE STUDY / 2024
LNG Export Terminal — Commissioning Support
- British Columbia, Canada
- 2024
- Pre-commissioning · Commissioning oversight · Operations readiness
SCHEMATIC
What PSG covered
THE BRIEF
What the client needed
A BC coastal LNG export terminal was approaching first cargo with construction substantially complete. The owner contracted PSG as an independent Approved Agency to verify mechanical completion and accompany the operations-readiness check-out, working alongside the EPC and the BC Oil and Gas Commission.
PSG'S APPROACH
What we did, in order
- 01
Mechanical completion audits across nine subsystems, with photographic evidence and code citations logged for each finding.
- 02
Electrical and instrumentation calibration witnessing, with deviations from approved procedures escalated within the shift in which they were observed.
- 03
Operations readiness review covering operator training records, procedural completeness, and emergency response drill outcomes.
- 04
Daily liaison with the BC OGC on-site representative; weekly summary report co-signed by PSG and the owner project lead.
OUTCOMES
What the engagement delivered
- 0BC OGC FINDINGS ON COMMISSIONING
- 9SUBSYSTEMS AUDITED
- 23PRE-STARTUP PUNCH ITEMS RESOLVED
- 2OPERATOR DRILL CYCLES WITNESSED
RELATED
Pillars and industries that touch this work
SERVICE PILLARS
INDUSTRIES
VERIFIED BY
Manisha Sharma, Project Lead · CGSB · BC OGC Approved Agency
REQUEST A PROPOSAL
Engage PSG on a similar project
Tell us what you need. We respond within one business day with named project leads and a rough scope estimate. No discovery-call gauntlet.